Installation, commissioning and inspection of chemical mixing tanks
Oct 29, 2018

Before installing and debugging the chemical mixing tank, it is necessary to check whether the equipment is seriously damaged and severely deformed during transportation, and whether the fasteners of the equipment are loose or not; then, by means of pre-buried anchor bolts, it is firm. The device is installed horizontally based on it.

 

The installation of the chemical mixing tank and its electrical control devices and accessories needs to be carried out under the guidance of a professional, and check whether the pipeline is unblocked, whether the installed instrument is correct, and whether there is any damage. Before starting the equipment, please check whether there are people or objects inside and outside the equipment that affect the normal operation of the equipment to avoid danger.

 

After the chemical mixing tank is installed, please perform a trial run for a few seconds to confirm that there is no electrical short circuit or no abnormal sound before a short test run. If the chemical mixing tank is equipped with a mechanical seal, an appropriate amount of 10# or sewing machine oil must be injected into the lubrication groove of the machine seal before the start of the main machine. The cooling water must be introduced into the cooling chamber of the machine seal so that the machine sealing device is well lubricated. And cooling.

 

Since the machine seal of the chemical mixing tank is not adjusted at the factory, after installation, the machine should be adjusted to the best position according to the installation and operation instructions before it can operate normally. After the equipment is in normal operation, please check the bearing temperature, smoothness of operation, tightness, etc., and whether the meter is normal.http://www.wxlsshzb.com/


Previous: How to divide the heat exchanger according to the heat transfer principle and the characteristics of the plate heat exchanger

Next: Discharge requirements and precautions for storage containers